Benchmarks & Client Cases

Accelerated Product Development

The Challenge

Problem


• Technical difficulty: develop a new, cheaper, smaller and more efficient water heater

• Extremely long lead-time (28 months)

• Reduction in time-to-market essential to increase sales



Root Causes


• Planning lacking any specific details and includes only the major milestones

• Plan not visible and not known by all stakeholders

• Tasks planned with a lot of safety (buffer)

• Poor integration of functions and suppliers

The Solution

• Optimised Pull Planning with buffers

• Obeya Room (Visual Project Management)

• Daily KAIZEN™ for Engineering and Testing Teams

• Last Planner with supplier integration

The Results

The project resulted in a saving of 84 man-months and a vertical production and market start-up.


time-to-market

Time-to-market

The time-to-market for the product decreased by 25%

development-costs-benefits

Development costs

Product development costs decreased by 24%