Benchmarks & Client Cases

Production Efficiency in Process Industry

The Challenge

process-detail-mapping
root-cause-analysis

Problem


• Breakdown Maintenance losses of 14.7 hours/month

• Total duration of planned stoppages over the course of one year was 168.1 hours

• Average setup time of 74 min

• Quality losses of 9.15%



Root Causes


• Lack of information on unplanned stoppages and ad-hoc resolution of problems

• Performance losses due to lack of standard parameters for production

• Inefficient planned stoppages due to poor diagnosis, lack of resource allocation, material preparation and team coordination

• Micro-stoppages in paper transformation and undefined setup activities

• Suboptimal planning sequences

The Solution

war-room-production-planning
autonomous-maintenance-zero-defects

• Structured Problem-Solving approach for unplanned stoppages, supported by detailed data

• Definition of optimal production parameters

• Standardised procedures and operators training

• More frequent planned stoppages managed through project management tools such as Last Planner, Risk Analysis and Task KANBAN

• Autonomous maintenance to reduce micro-stoppages during paper transformation

• Production sequencing guidelines and process standardisation to minimise setup activities

The Results

The project had a Payback period of 4 months with annual savings surpassing £1.7 million.


breadown-benefits

Breakdown

As a result of maintenance issues, breakdown times reduced by 20%

Planned Stoppages

Planned Stoppages

Time for planned stoppages reduced by 26%

Quality losses

Quality losses

Volume of quality losses reduced by 4%

setup-time-benefits

Setup Time

Logistics productivity increase by 31% with optimisation of layouts and containers