Speed of Innovation

The Challenge



innovation-process-improvements

Problem


• Lengthy development Lead Time

• Last stage of the project plagued with rejects and rework

• Not enough development capacity

• Sales are not maximised by dropping customer requirements throughout the process



Root Causes


• Lack of communication between departments

• Rigid and bureaucratic process

• Development focus only on closed concept

• Inputs and exchanged requirements throughout the process

The Solution

new-process-design-innovation

• Obeya control and standardisation of Lean scheduling to increase communication

• Customer interests events, feasibility planning, learning cycles and integrating events to improve project quality

• Flow cells creation to reduce project Lead Time

• Documentation Standard Work to reduce project cost

The Results

The project had a payback period of less than 3 months with annual Savings of £4.5 million.



sales-forecast-benefits

Real Sales vs Forecast Sales

Accuracy of sales forecast increased by 18%

development-effort-benefits

Development Productivity

Development productivity increased by 8.6%

project-lead-time-benefits

Project Lead Time

Project Lead Time reduced by 50%